The new PDI for vehicle preparation was developed in 1972 and is divided into the sub-areas of car wash, bodywork, mechanics and finish. Following a concept study, it was decided in October 2016 that the building should make way for a new building.
Events:Previous planning: October 2016: concept study decision new building May 2018: provisional study decision January 2019: building application for the operations center and temporary facility Further planning: Spring 2019: start of construction + temporary agreements Summer 2019: building application for a new building PDI Spring 2020: start of construction phase 1 new building PDI Spring 2021: completion of construction work